0151 207 7740 enquiries@cdmengland.co.uk
Project:

Ligna Biomass - Port of Liverpool

CDM England Role:

CDM Scotland Ltd acted as the CDM Coordinator and Client Safety Advisor for the project.

Contract Value:

£100,000,000

Project Team:
Mark Cook - Director
Our Services:
  • CDM Coordinator
  • Client Safety Advisor
The project comprises the design and build and a new biomass import, storage and out loading facility at the Port of Liverpool. The works include construction of 3 storage silos, conveyor system and rail installation (approx. 6km) and new discharge facility. The project involved the breaking out of a heavily reinforced quay to allow the construction of a below ground conveyor system to feed the rail load out and silo systems. The works also included the construction of a rail loadout facility linked to the silos via the conveyor system.